Ray Properties Kit Carson Inc.
Survey Date: Wednesday, August 13, 2014
Survey Type: Health
Deficiency: F0353 (Have enough nurses to care for every resident in a way that maximizes the resident's well being.)
Scope Severity Code: F
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Tuesday, September 9, 2014
The inspection cycle of deficiency: 1 (the deficiency was found on a complaint inspection)
Survey Date: Monday, August 11, 2014
Survey Type: Health
Deficiency: F0257 (Maintain comfortable and safe temperature levels.)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Wednesday, September 10, 2014
The inspection cycle of deficiency: 1 (the deficiency was found on a complaint inspection)
Survey Date: Monday, June 23, 2014
Survey Type: Health
Deficiency: F0241 (Provide care for residents in a way that maintains or improves their dignity and respect in full rec)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Monday, July 7, 2014
The inspection cycle of deficiency: 1 (the deficiency was found on a complaint inspection)
Survey Date: Thursday, December 5, 2013
Survey Type: Fire Safety
Deficiency: K0054 (Properly maintained smoke detectors.)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Wednesday, January 1, 2014
The inspection cycle of deficiency: 1 (the deficiency was found on a standard inspection)
Survey Date: Thursday, December 5, 2013
Survey Type: Fire Safety
Deficiency: K0046 (Emergency lighting that can last at least 1 1/2 hours.)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Wednesday, January 1, 2014
The inspection cycle of deficiency: 1 (the deficiency was found on a standard inspection)
Survey Date: Thursday, December 5, 2013
Survey Type: Fire Safety
Deficiency: K0144 (Weekly inspections and monthly testing of generators.)
Scope Severity Code: C
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Wednesday, January 1, 2014
The inspection cycle of deficiency: 1 (the deficiency was found on a standard inspection)
Survey Date: Thursday, December 5, 2013
Survey Type: Fire Safety
Deficiency: K0052 (An approved installation, maintenance and testing program for fire alarm systems.)
Scope Severity Code: E
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Wednesday, January 1, 2014
The inspection cycle of deficiency: 1 (the deficiency was found on a standard inspection)
Survey Date: Thursday, December 5, 2013
Survey Type: Fire Safety
Deficiency: K0064 (Portable fire extinguishers.)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Wednesday, January 1, 2014
The inspection cycle of deficiency: 1 (the deficiency was found on a standard inspection)
Survey Date: Thursday, December 5, 2013
Survey Type: Fire Safety
Deficiency: K0062 (Automatic sprinkler systems that have been maintained in working order.)
Scope Severity Code: F
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Wednesday, January 1, 2014
The inspection cycle of deficiency: 1 (the deficiency was found on a standard inspection)
Survey Date: Thursday, December 5, 2013
Survey Type: Fire Safety
Deficiency: K0022 (Signs that state that exit doors are to be kept closed.)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Wednesday, January 1, 2014
The inspection cycle of deficiency: 1 (the deficiency was found on a standard inspection)
Survey Date: Thursday, December 5, 2013
Survey Type: Fire Safety
Deficiency: K0069 (Properly protected cooking facilities.)
Scope Severity Code: E
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Wednesday, January 1, 2014
The inspection cycle of deficiency: 1 (the deficiency was found on a standard inspection)
Survey Date: Thursday, December 5, 2013
Survey Type: Fire Safety
Deficiency: K0047 (Properly located and lighted "Exit" signs.)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Wednesday, January 1, 2014
The inspection cycle of deficiency: 1 (the deficiency was found on a standard inspection)
Survey Date: Thursday, December 5, 2013
Survey Type: Fire Safety
Deficiency: K0051 (A fire alarm system that can be heard throughout the facility.)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Wednesday, January 1, 2014
The inspection cycle of deficiency: 1 (the deficiency was found on a standard inspection)
Survey Date: Thursday, December 5, 2013
Survey Type: Fire Safety
Deficiency: K0147 (Properly installed electrical wiring and equipment.)
Scope Severity Code: E
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Wednesday, January 1, 2014
The inspection cycle of deficiency: 1 (the deficiency was found on a standard inspection)
Survey Date: Thursday, December 5, 2013
Survey Type: Fire Safety
Deficiency: K0076 (Proper medical gas storage and administration areas.)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Wednesday, January 1, 2014
The inspection cycle of deficiency: 1 (the deficiency was found on a standard inspection)
Survey Date: Thursday, December 5, 2013
Survey Type: Fire Safety
Deficiency: K0018 (Corridor and hallway doors that block smoke.)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Wednesday, January 1, 2014
The inspection cycle of deficiency: 1 (the deficiency was found on a standard inspection)
Survey Date: Thursday, November 21, 2013
Survey Type: Health
Deficiency: F0314 (Give residents proper treatment to prevent new bed (pressure) sores or heal existing bed sores.)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Wednesday, January 8, 2014
The inspection cycle of deficiency: 1 (the deficiency was found on a standard inspection)
Survey Date: Thursday, November 21, 2013
Survey Type: Health
Deficiency: F0360 (Provide a tasty and well-balanced diet that meets the nutritional needs of each resident.)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Wednesday, January 8, 2014
The inspection cycle of deficiency: 1 (the deficiency was found on a standard inspection)
Survey Date: Thursday, November 21, 2013
Survey Type: Health
Deficiency: F0325 (Ensure residents maintain acceptable nutritional status.)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Wednesday, January 8, 2014
The inspection cycle of deficiency: 1 (the deficiency was found on a standard inspection)
Survey Date: Thursday, November 21, 2013
Survey Type: Health
Deficiency: F0334 (Develop policies and procedures for influenza and pneumococcal immunizations.)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Wednesday, January 8, 2014
The inspection cycle of deficiency: 1 (the deficiency was found on a standard inspection)
Survey Date: Thursday, November 21, 2013
Survey Type: Health
Deficiency: F0323 (Ensure that a nursing home area is free from accident hazards and provide adequate supervision to pr)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Wednesday, January 8, 2014
The inspection cycle of deficiency: 1 (the deficiency was found on a standard inspection)
Survey Date: Thursday, November 21, 2013
Survey Type: Health
Deficiency: F0431 (Maintain drug records and properly mark/label drugs and other similar products according to accepted)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Wednesday, January 8, 2014
The inspection cycle of deficiency: 1 (the deficiency was found on a standard inspection)
Survey Date: Thursday, November 21, 2013
Survey Type: Health
Deficiency: F0221 (Keep each resident free from physical restraints, unless needed for medical treatment.)
Scope Severity Code: E
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Wednesday, January 8, 2014
The inspection cycle of deficiency: 1 (the deficiency was found on a standard inspection)
Survey Date: Monday, March 11, 2013
Survey Type: Health
Deficiency: F0157 (Immediately tell the resident, the resident's doctor, and a family member of situations (injury/decl)
Scope Severity Code: G
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Tuesday, April 16, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a complaint inspection)
Survey Date: Tuesday, January 15, 2013
Survey Type: Health
Deficiency: F0223 (Protect each resident from all abuse, physical punishment, and involuntary separation from others.)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Thursday, January 31, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a complaint inspection)
Survey Date: Monday, January 14, 2013
Survey Type: Health
Deficiency: F0241 (Provide care for residents in a way that maintains or improves their dignity and respect in full rec)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Thursday, January 31, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a complaint inspection)
Survey Date: Monday, December 17, 2012
Survey Type: Fire Safety
Deficiency: K0064 (Portable fire extinguishers.)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Tuesday, January 15, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a standard inspection)
Survey Date: Monday, December 17, 2012
Survey Type: Fire Safety
Deficiency: K0047 (Properly located and lighted "Exit" signs.)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Tuesday, January 15, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a standard inspection)
Survey Date: Monday, December 17, 2012
Survey Type: Fire Safety
Deficiency: K0046 (Emergency lighting that can last at least 1 1/2 hours.)
Scope Severity Code: E
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Tuesday, January 15, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a standard inspection)
Survey Date: Monday, December 17, 2012
Survey Type: Fire Safety
Deficiency: K0076 (Proper medical gas storage and administration areas.)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Tuesday, January 15, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a standard inspection)
Survey Date: Monday, December 17, 2012
Survey Type: Fire Safety
Deficiency: K0147 (Properly installed electrical wiring and equipment.)
Scope Severity Code: E
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Tuesday, January 15, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a standard inspection)
Survey Date: Monday, December 17, 2012
Survey Type: Fire Safety
Deficiency: K0062 (Automatic sprinkler systems that have been maintained in working order.)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Tuesday, January 15, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a standard inspection)
Survey Date: Monday, December 17, 2012
Survey Type: Fire Safety
Deficiency: K0072 (Exits that are free from obstructions and can be used at all times.)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Tuesday, January 15, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a standard inspection)
Survey Date: Monday, December 17, 2012
Survey Type: Fire Safety
Deficiency: K0018 (Corridor and hallway doors that block smoke.)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Tuesday, January 15, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a standard inspection)
Survey Date: Thursday, December 6, 2012
Survey Type: Health
Deficiency: F0364 (Prepare food that is nutritional, appetizing, tasty, attractive, well-cooked, and at the right tempe)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Thursday, January 3, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a standard inspection)
Survey Date: Thursday, December 6, 2012
Survey Type: Health
Deficiency: F0323 (Ensure that a nursing home area is free from accident hazards and provide adequate supervision to pr)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Thursday, January 3, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a standard inspection)
Survey Date: Thursday, December 6, 2012
Survey Type: Health
Deficiency: F0314 (Give residents proper treatment to prevent new bed (pressure) sores or heal existing bed sores.)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Thursday, January 3, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a standard inspection)
Survey Date: Thursday, December 6, 2012
Survey Type: Health
Deficiency: F0514 (Keep accurate, complete and organized clinical records on each resident that meet professional stand)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Thursday, January 3, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a standard inspection)
Survey Date: Thursday, December 6, 2012
Survey Type: Health
Deficiency: F0461 (Make sure each resident has 1) at least one window to the outside in a room; 2) a room at or above g)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Thursday, January 3, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a standard inspection)
Survey Date: Thursday, December 6, 2012
Survey Type: Health
Deficiency: F0431 (Maintain drug records and properly mark/label drugs and other similar products according to accepted)
Scope Severity Code: E
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Thursday, January 3, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a standard inspection)
Survey Date: Thursday, December 6, 2012
Survey Type: Health
Deficiency: F0425 (Provide routine and emergency drugs through a licensed pharmacist and only under the general supervi)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Thursday, January 3, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a standard inspection)
Survey Date: Thursday, December 6, 2012
Survey Type: Health
Deficiency: F0505 (Quickly tell the resident's doctor the results of laboratory tests.)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Thursday, January 3, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a standard inspection)
Survey Date: Thursday, December 6, 2012
Survey Type: Health
Deficiency: F0329 (Ensure that each resident's 1) entire drug/medication regimen is free from unnecessary drugs; and 2))
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Thursday, January 3, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a standard inspection)
Survey Date: Thursday, December 6, 2012
Survey Type: Health
Deficiency: F0246 (Reasonably accommodate the needs and preferences of each resident.)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Thursday, January 3, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a standard inspection)
Survey Date: Thursday, December 6, 2012
Survey Type: Health
Deficiency: F0309 (Provide necessary care and services to maintain or improve the highest well being of each resident .)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Thursday, January 3, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a standard inspection)
Survey Date: Thursday, December 6, 2012
Survey Type: Health
Deficiency: F0328 (Properly care for residents needing special services, including: injections, colostomy, ureostomy, i)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Thursday, January 3, 2013
The inspection cycle of deficiency: 2 (the deficiency was found on a standard inspection)
Survey Date: Thursday, October 18, 2012
Survey Type: Health
Deficiency: F0226 (Develop and implement policies for 1) screening and training employees; and the 2) prevention, ident)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Wednesday, November 7, 2012
The inspection cycle of deficiency: 2 (the deficiency was found on a complaint inspection)
Survey Date: Tuesday, November 15, 2011
Survey Type: Fire Safety
Deficiency: K0062 (Automatic sprinkler systems that have been maintained in working order.)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Thursday, December 8, 2011
The inspection cycle of deficiency: 3 (the deficiency was found on a standard inspection)
Survey Date: Tuesday, November 15, 2011
Survey Type: Fire Safety
Deficiency: K0070 (Restrictions on the use of portable space heaters.)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Thursday, December 8, 2011
The inspection cycle of deficiency: 3 (the deficiency was found on a standard inspection)
Survey Date: Tuesday, November 15, 2011
Survey Type: Fire Safety
Deficiency: K0018 (Corridor and hallway doors that block smoke.)
Scope Severity Code: E
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Thursday, December 8, 2011
The inspection cycle of deficiency: 3 (the deficiency was found on a standard inspection)
Survey Date: Tuesday, November 15, 2011
Survey Type: Fire Safety
Deficiency: K0029 (Special areas constructed so that walls can resist fire for one hour or an approved fire extinguishi)
Scope Severity Code: E
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Thursday, December 8, 2011
The inspection cycle of deficiency: 3 (the deficiency was found on a standard inspection)
Survey Date: Tuesday, November 15, 2011
Survey Type: Fire Safety
Deficiency: K0076 (Proper medical gas storage and administration areas.)
Scope Severity Code: E
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Thursday, December 8, 2011
The inspection cycle of deficiency: 3 (the deficiency was found on a standard inspection)
Survey Date: Tuesday, November 15, 2011
Survey Type: Fire Safety
Deficiency: K0046 (Emergency lighting that can last at least 1 1/2 hours.)
Scope Severity Code: E
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Thursday, December 8, 2011
The inspection cycle of deficiency: 3 (the deficiency was found on a standard inspection)
Survey Date: Tuesday, November 15, 2011
Survey Type: Fire Safety
Deficiency: K0144 (Weekly inspections and monthly testing of generators.)
Scope Severity Code: E
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Thursday, December 8, 2011
The inspection cycle of deficiency: 3 (the deficiency was found on a standard inspection)
Survey Date: Tuesday, November 15, 2011
Survey Type: Fire Safety
Deficiency: K0147 (Properly installed electrical wiring and equipment.)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Thursday, December 8, 2011
The inspection cycle of deficiency: 3 (the deficiency was found on a standard inspection)
Survey Date: Tuesday, November 15, 2011
Survey Type: Fire Safety
Deficiency: K0047 (Properly located and lighted "Exit" signs.)
Scope Severity Code: E
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Thursday, December 8, 2011
The inspection cycle of deficiency: 3 (the deficiency was found on a standard inspection)
Survey Date: Thursday, November 10, 2011
Survey Type: Health
Deficiency: F0514 (Keep accurate, complete and organized clinical records on each resident that meet professional stand)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Wednesday, December 21, 2011
The inspection cycle of deficiency: 3 (the deficiency was found on a standard inspection)
Survey Date: Thursday, November 10, 2011
Survey Type: Health
Deficiency: F0311 (Make sure that residents receive treatments/services to maintain or improve their ability to care fo)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Wednesday, December 21, 2011
The inspection cycle of deficiency: 3 (the deficiency was found on a standard inspection)
Survey Date: Thursday, November 10, 2011
Survey Type: Health
Deficiency: F0325 (Ensure residents maintain acceptable nutritional status.)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Wednesday, December 21, 2011
The inspection cycle of deficiency: 3 (the deficiency was found on a standard inspection)
Survey Date: Thursday, November 10, 2011
Survey Type: Health
Deficiency: F0518 (Train all employees on what to do in an emergency, and carry out unannounced staff drills.)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Wednesday, December 21, 2011
The inspection cycle of deficiency: 3 (the deficiency was found on a standard inspection)
Survey Date: Thursday, November 10, 2011
Survey Type: Health
Deficiency: F0517 (Have a detailed, written plan for disasters and emergencies, such as fire, severe weather, and missi)
Scope Severity Code: D
Deficiency Corrected: Deficient, Provider Has Date Of Correction
Date the deficiency was corrected: Wednesday, December 21, 2011
The inspection cycle of deficiency: 3 (the deficiency was found on a standard inspection)